What key benefits might stakeholders realize from an Agile approach?
A. The ability to bypass the change-management process Drew Sample Jersey , inserting new requirements and changes directly into the team as they meet daily B. The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments C. Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting D. The t lity to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments
Answer: B tion aligned with the project management plan B. A disciplined iteration schedule, which improves predictability, combined with reaction to changes C. Ball park figures collected from past Agile projects with scopes similar to the current project D. Initial resource breakdown based on the available person days in the full project duration
Answer: B
Question: 9
A value stream map is a tool used to identify the:
A. Waste across the entire process. B. Highest value product features. C. Most valuable team interactions. D. Most likely flow of project risks.
Answer: A
Question: 10
When estimating initial velocity, the team should most likely: